Section 404 Clean Water Act

Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Kyle Dahl
POC Title:
Team Leader

Description:

Bureau of Indian Affairs-Pacific Regioin will consult with the United States Army Corps of Engineers to obtain a Nationwide Permit for the Campo Wind Project.  A separate Construction General Permit (CGP) may be required for this project to be issued by USEPA.

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Current Target Date:
Milestone Details

BIA is delaying submittal of the PCN to accommodate review of the proposed aquatic resources delineation report and to conclude consultation requirements.

Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Current Target Date:
Milestone Details

BIA is delaying submittal of the PCN to accommodate review of the proposed aquatic resources delineation report and to conclude consultation requirements.

Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The Corps is anticipating issuance of the 404 NWP within 90 days of signature of the ROD. Corps has coordinated scheduling with BIA, most critically the conclusion of Federal consultation requirements to facilitate issunace of the Corps permit in the time frame.