Project Name:
Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status:
Cooperating under NEPA
Status:
Planned
Milestones:
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
3876
Current Target Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
3881
Current Target Date:
Final Verification/Permit Decision Rendered (Agency Action)
3891
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 03/07/2022 -
State, Local, Tribal, or Other Non-Federal Action
:
Final decision/agency action (Agency Action)
- Current Target Date: 01/31/2028
Current Target Date: