Fish and Wildlife Coordination Act Review (DOI – FWS)

Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Paused
POC Name:
Chuck Ardizzone
POC Title:
Project Leader
Action Outcome:
FWCA recommendations to conserve, mitigate, or enhance fish and wildlife resources issued

Description:

For Buffalo Bayou & Tribs the Corps (SWG) will develop a draft Coordination Act Report in coordination with the Clear Lake USFWS office and deliver this drat CAR to the FWS office by end of June 2020 when the Draft Final report is released.  By October 13th, 2020 the Corps and FWS expect to have a complete CAR.  The Corps and USFWS will continue coordination after October 13th and reach a final CAR by December 31, 2020.

Milestones:

Action Agency requests consultation regarding conservation of fish and wildlife resources (Agency Action)
Current Target Date:
Fish and Wildlife Coordination Act review concluded (Agency Action)
Current Target Date: