Endangered Species Act Consultation (NOAA-NMFS)

Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Julie Crocker
POC Title:
Endangered Fish Branch Chief, GARFO Protected Resources Division

Description:

Endangered Species Act Section 7 consultation. *The initiation and final completion dates are contingent upon NMFS receiving what it concludes is adequate information to initiate ESA consultation.

ESA-listed species exist throughout the area affected by the wind farm and associated transmission line.  The proposed action will adversely affect these resources, therefore formal ESA Section 7 consultation is required.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Current Target Date:
Milestone Details

Target: Consultation request expected concurrent with BOEM’s issuance of the draft EIS. *This target timeline is dependent on receipt of a complete consultation request from BOEM, including a Biological Assessment, which is expected concurrent with issuance of the draft EIS.

NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
Milestone Details

Target: Concurrent with receipt of a complete Biological Assessment (expected concurrent with release of DEIS). *This target timeline is dependent on receipt of a complete consultation request from BOEM, including a Biological Assessment, that NMFS concludes has adequate information to initiate ESA consultation.

ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone Details

Target: 135 days following the Consultation Initiation Date. *The final completion date is contingent upon NMFS receiving sufficient information to initiate formal ESA consultation.