Project Name:
Responsible Agency:
Federal Railroad Administration
Status:
Complete
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
3506
Completed Date:
Scoping (Agency Action)
3511
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
3516
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
3521
Completed Date:
Issuance of Lead Agency Record of Decision (Agency Action)
3536
Completed Date: