West Seattle and Ballard Link Extensions Project EIS

PROJECT WEBSITE: West Seattle and Ballard Link Extensions Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The West Seattle and Ballard Link Extensions project proposed by Sound Transit would expand Link light rail from downtown Seattle to West Seattle’s Alaska Junction area and Ballard’s Market Street area in Seattle, King County, Washington. The project is approximately 11.8 miles. It includes a mix of elevated, at-grade, and tunnel configurations and fourteen stations that serve the following areas: Alaska Junction, Avalon, Delridge, SODO, the sports stadiums, International District/Chinatown, Midtown, Westlake, Denny, South Lake Union, Seattle Center, Smith Cove, Interbay, and Ballard. The project would provide a dependable and efficient connection along the corridor and respond to a growing number of transportation and community needs. In addition to build alternatives, the project will also consider a No Build alternative.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete