USA logoAn Official Website of the United States Government

You are here

Vineyard Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE
Nov 14 2019
0 OUT OF 7
ENVIRONMENTAL REVIEW
AND PERMITTING PROCESSES COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Major Infrastructure Projects
LEAD AGENCY
Department of the Interior
Description: 

The Vineyard Wind project would involve the construction, operation, maintenance and eventual decommissioning of an up to 800 MW wind energy facility on the Federal Outer Continental Shelf approximately 14 miles southeast of Martha’s Vineyard.  Vineyard Wind’s construction and operations plan (COP) proposes installing up to 100 wind turbine generators, each with a capacity of between 8 and 10 MW. Foundations would be 100 monopiles or up to 10 jacket foundations and the remainder monopiles. The proposed facility would also include one or two offshore substations or electrical service platforms. The Vineyard Wind COP also proposes an export cable from the wind energy facility to one of two potential export cable landfalls: one near the town of Yarmouth and one near the town of Barnstable, both in the Commonwealth of Massachusetts. Onshore construction and staging would take place at the New Bedford Marine Commerce Terminal facility. The turbines would be located in water depths ranging from approximately 37 to 49 meters (approximately 121 to 161 feet).

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.

To view Timetable chart, please turn device sideways (landscape)

Overall Project Timetable
STATUS
Schedule
Extension
Ahead of Schedule
Paused

Action Information

For additional information, please select an Action from the Permitting Timetable above.

Action:
Responsible Agency:
Bureau:
Action Status:
SHPO:
Action Identifier:
Action Outcome:
Milestone
Original Target Date
Current Target Date
Milestone Complete