US 59 Corrigan Relief Route
PROJECT WEBSITE: US 59 North / Loop 287
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/30/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The proposed project consists of constructing a new location relief route west of US 59 from approximately 3.4 miles north of US 287 to 2.3 miles south of US 287 in the City of Corrigan, Texas. The proposed relief route would provide a four lane controlled access freeway with a provision for future expansion to an ultimate 6-lane freeway section, ramps and grade separations on the north and south ends at the Union Pacific Railroad (UPR) and US 287 and additional bridges over creek crossings and Union Springs Rd. No frontage roads are proposed.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|