Upper Barataria Basin Feasibility Study

PROJECT WEBSITE: Upper Barataria Basin

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/08/2021

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources icon

SECTOR
Water Resources

CATEGORY
Major Infrastructure Projects

Department of the Army icon

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Pursuant to the National Environmental Policy Act (NEPA), the U.S. Army Corps of Engineers, New Orleans District (USACE) intends to prepare a Draft Integrated Feasibility Report and Environmental Impact Statement (DIFR–EIS) to assess the potential social, economic, and environmental impacts associated with the proposed project titled, Upper Barataria Basin Coastal Feasibility Study. The DIFR–EIS will document the existing condition of environmental resources in and around areas considered for construction, and potential impacts on those resources as a result of implementing the alternatives.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete