Official US Government Icon

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

Secure Site Icon

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Turkey Point, Units 6 and 7

PROJECT WEBSITE: http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/18/2019

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production icon

SECTOR
Conventional Energy Production

CATEGORY
FAST-41 Covered Projects

Nuclear Regulatory Commission icon

LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors

Description:

The USACE proffered the remaining permit to the project sponsor (Florida Power and Light) December 18, 2019.

Florida Power and Light Company (FPL), seeks approval for constructing and operating two new AP1000 reactor units at the Turkey Point site to provide additional electricity for use in the Southern Florida service areas.  The two new units would be capable of providing an additional 2200 megawatts of baseload electricity.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete