Official US Government Icon

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

Secure Site Icon

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Transwest Express

PROJECT WEBSITE: TransWest

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/19/2017

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission icon

SECTOR
Electricity Transmission

CATEGORY
FAST-41 Covered Projects

Department of the Interior icon

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

TransWest Express, LLC, sponsors the project, which consists of a 725-mile 600kV DC line from Sinclair, WY substation to Marketplace, NV substation.  The project is a 3 billion dollar project designed to carry renewable and other energy generated in Wyoming to the desert southwest. 

The Bureau of Land Management (BLM) issued the Final Environmental Impact Statement (FEIS) in May 2016. The BLM completed agency and Tribal government consultations, and issued a Record of Decision December 2016, with the ROD Notice of Availability publication in the Federal Register December 16, 2016.  The project was paused temporarily awaiting action from the sponsor; BLM resumed processing in May 2017 and the ROW Grant was issued June 20.2017.  Section 107 and Section 106 consultations were completed prior to initiation under FAST-41, and thus are not included on the permitting timetable.  Information, including NEPA documentation, can be found on the TransWest project page:  http://bit.ly/TransWestExpress

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete