Official US Government Icon

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

Secure Site Icon

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Surry-Skiffes Creek-Whealton Aerial Transmission Line

PROJECT WEBSITE: Dominion Power Surry-Skiffes Creek-Whealton Corps Permit Application Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission icon

SECTOR
Electricity Transmission

CATEGORY
Major Infrastructure Projects

Department of the Army icon

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

Description:

Virginia Electric and Power Company (Dominion) has proposed an electrical transmission powerline and associated infrastructure, known as Surry-Skiffes Creek-Whealton project. The proposed project involves a 7.76-mile 500 kV overhead transmission powerline from Surry nuclear power plant in Surry County to the proposed Skiffes Creek 500 kV-230 kV-115 kV switching station, on 51 acres of private and commercial property in James City County, and 20.2 miles of 230 kV overhead powerline along an existing right of way from the switching station to Whealton substation in Hampton. In July 2017, the U.S. Army Corps of Engineers (Corps) issued an Individual Permit for the Project under Section 404 of the Clean Water Act (33 U.S.C. 1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403), as well as a permission letter under RHA Section 408. As part of its review process, the Corps prepared an environmental assessment (EA), which is available at the Corps' project website (https://www.nao.usace.army.mil/ Missions/ Regulatory/ SkiffesCreekPowerLine.aspx). Among other conditions, the permit was issued subject to compliance with a 2017 Memorandum of Agreement (MOA) executed by the Corps; Dominion; and the Acting Assistant Secretary of the Interior for Fish, Wildlife, and Parks (on behalf of the National Park Service (NPS)), among other parties. The MOA, developed through the National Historic Preservation Act Section 106 consultation process, contained stipulations to avoid, minimize, and mitigate impacts to the historic properties in proximity to the proposed project. Dominion proceeded with construction of the project pursuant to the Corps permit and its conditions, including the conditions set forth in the MOA. The Corps permit was challenged in the U.S. District Court for the District of Columbia, which awarded summary judgment to the Corps and upheld the permit decision. That decision was appealed. In National Parks Conservation Association v. Semonite, No. 18-5179, the United States Court of Appeals for the District of Columbia Circuit remanded this action to the district court with instructions to direct the Corps to prepare an EIS pursuant to the National Environmental Policy Act (NEPA). Consistent with the court's decision, Dominion seeks authorization from the Corps for the original proposed project whose construction is approximately 99 percent complete and scheduled for completion by October 2019. On February 26, 2019, Dominion Energy electrically energized the Project.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete