SR 87 Connector (from SR 87 S Intersecting with SR 87 N near Southridge Rd)
PROJECT WEBSITE: SR 87 Connector PD&E Study
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/20/2016
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The primary objectives in the extension of SR 87S is to facilitate a more effective freight movement and hurricane evacuation route from the coast, reduce congestion in the City of Milton, and to alleviate travel demand on US 90. The study will focus on addressing transportation needs as it relates to:
- Improving mobility,
- Relieving traffic congestion and improving traffic circulation,
- Improving upon pedestrian and bicycle connectivity,
- Providing efficient access to/from the beach (SR 87 is also an important Hurricane Evacuation Route), and
- Providing for and ensuring public safety, while protecting the environment.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|