SR 47 Interchange Reconfiguration
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/08/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
California
Description:
The California Department of Transportation (Caltrans), in cooperation with the City of
Los Angeles Harbor Department (LAHD), proposes to reconfigure the existing
interchange at State Route 47 (SR-47)/Vincent Thomas Bridge and Harbor
Boulevard/Front Street. The project limits on SR-47 extend from approximately Post
Mile [PM] 0.3 to PM 0.8 (SR-47 from west of Harker Street to east of North Front Street)
in the City of Los Angeles in Los Angeles County, California.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|