SR 101: San Jose Creek Bridge Replacement

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-5/district-5-current-projects/san-…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/28/2022

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

California

California

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The California Department of Transportation (Caltrans) proposes to replace the existing northbound and southbound San Jose Creek Bridges, which are located in the City of Goleta in Santa Barbara County on U.S. Route 101 (US-101) at Post Mile (PM) 21.6. US-101 runs through California, Oregon, and Washington and connects cities located along its alignment. Within project limits, US-101 consists of a six-lane concrete conventional highway, with three lanes in each direction. The area surrounding the proposed project is primarily urban and residential, but also includes commercial and industrial land uses.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete