Southern and Eastern Wake Expressway, "Complete 540"
PROJECT WEBSITE: Complete 540
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/06/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The proposed project, also known as the "Complete 540" or Southeast Extension, would extend the Triangle Expressway from the N.C. 55 Bypass in Apex to the U.S. 64/U.S. 264 Bypass in Knightdale, completing the 540 Outer Loop around the greater Raleigh area.
Transportation, social and economic demands and mobility considerations are the basis for additional transportation infrastructure in southeastern Wake County. The "Complete 540" project would link the towns of Apex, Cary, Clayton, Garner, Fuquay-Varina, Holly Springs and Raleigh. In addition to connecting several towns and cities, the project is anticipated to ease congestion on area roadways, including I-440, I-40, N.C. 42, N.C. 55 and Ten Ten Road.
Complete 540 consists of three separate NCDOT projects (R-2721, R-2828, and R-2829) that are combined for the current planning and environmental study. Construction will likely be done in phases that correspond to these three individual projects. Depending on available funding, each project will likely have different construction time lines.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|