Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Round Hill Pines Access Project

PROJECT WEBSITE: https://flh.fhwa.dot.gov/projects/nv/round-hill-pines/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Nevada icon

COOPERATING AGENCY Nevada

Description:

FHWA-CFLHD, in cooperation with USDA Forest Service Lake Tahoe Basin Management Unit, Nevada DOT, and the Tahoe Regional Planning Agency, is proposing to improve safety for visitors entering and exiting the Round Hill Pines Resort from U.S. Highway 50. The project begins south of the existing entrance road into the resort and extends north along US Highway 50 for approximately 0.35 mile. The Project is located in Douglas County near Zephyr Cove, Nevada.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete