Official US Government Icon

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

Secure Site Icon

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

R.C. Byrd

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Cancelled icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production icon

SECTOR
Renewable Energy Production

CATEGORY
FAST-41 Covered Projects

Federal Energy Regulatory Commission icon

LEAD AGENCY
Federal Energy Regulatory Commission

Description:

R.C. Byrd (Project No. 12796) is a proposal to construct an original 50 MW conventional hydropower project adjacent to the right abutment of the existing  U.S. Army Corps of Engineers' (Corps) Robert C. Byrd Locks and Dam on the Ohio River.  The transmission line would cross the Ohio River from the proposed power plant and traverse private land and the Corps' land within West Virginia.  

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

Last updated December 5, 2019

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete