Dot gov

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

SSL

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Plains Pipeline, L.P. Lines 901 and 903 Replacement Project

PROJECT WEBSITE: Replacement of Lines 901 and 903

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production icon

SECTOR
Conventional Energy Production

CATEGORY
FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior icon

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

The proposed Plains Pipeline will replace the existing pipelines known as Line 901 and Line 903 with the Line 901R and Line 903R pipelines. The proposed Project consists of the installation and operation of approximately 123.4 miles of replacement pipelines, supporting access roads, valves, and pump stations.

The proposed project is in the planned stage based on several factors. The applicant is preparing an application and Plan of Development for submittal to the project team. Until the application and Plan of Development is received, the proposed project may not be Initiated. In addition, a NEPA contractor is needed. The proposed project will be in the in progress stage in the First Quarter of Calendar Year 2019.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete