Plains Pipeline, L.P. Lines 901 and 903 Replacement Project

PROJECT WEBSITE: Replacement of Lines 901 and 903

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/30/2022

0 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production icon

SECTOR
Conventional Energy Production

CATEGORY
FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior icon

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of Commerce icon

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army icon

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior icon

Department of the Interior, Fish and Wildlife Service

Description:

Plains Pipeline, L.P. filed a right-of-way application with the Bureau of Land Management (BLM) Bakersfield Office on January 9, 2018, for the replacement and abandonment of existing oil pipelines 901 and 903. The project spans multiple local, State and Federal jurisdictions. The proposed project consists of installation and operation of approximately 123.4 miles of replacement pipelines 901R and 903R, supporting access roads, valves, and pump stations. 

The project was paused from November 1, 2019 to January 4, 2021. Plains Pipeline, L.P. submitted an updated project description and supporting documents during this time. A Standard Individual Permit (SIP) application was submitted to the United States Army Corps of Engineers on October 5, 2020 to replace the original Nation Wide Permit (NWP) 12 Per-Construction Notification(PCN) application while the project was in paused status.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete