Pacific Northwest Rail Corridor Program: Oregon Segment

PROJECT WEBSITE: http://www.oregonpassengerrail.org/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/17/2020

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The U.S. Department of Transportation’s (USDOT) Federal Railroad Administration (FRA) and the Oregon Department of Transportation (ODOT) are preparing a Tier 1 Environmental Impact Statement (EIS) to evaluate options for improved intercity passenger rail service along the approximately 130-mile segment of the federally designated Pacific Northwest Rail Corridor from the Eugene-Springfield urban area to the Washington state line at the Columbia River in Portland. This environmental review will help ODOT and FRA make decisions such as selecting the general rail alignment and communities where stations would be located and determining service characteristics, such as the number of daily trips, travel time objectives, and the technologies to be used.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete