Ocean Wind Project

PROJECT WEBSITE: Ocean Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/29/2023

0 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

OCW intends to develop, build, operate, and own (through one or more affiliated special purpose entities) a utility-scale offshore wind farm located approximately 15 miles off the coast of New Jersey within the Lease Area (the “Project”). The Project is being developed to serve the New Jersey market pursuant to the ongoing State of New Jersey’s Offshore Wind Economic Development Act Section 4 procurement process, administered by the New Jersey Board of Public Utilities (“NJBPU”). OCW was the sole beneficiary of New Jersey’s first 1,100 MW solicitation. Additional projects may also be developed within the Lease Area in the future in support of New Jersey Governor Phil Murphy’s Executive Order Number 8, which established a goal of developing 3.5 GW of offshore wind by 2030.1 Further solicitations by the NJBPU of 1,200 MW each are expected in 2020 and 2022.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete