National Trails Highway: Bridge Replacements

PROJECT WEBSITE: National Trails Highway

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

1 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

California icon

LEAD AGENCY
California

Description:

The County of San Bernardino is proposing to replace and rehabilitate 31 bridges on the National Trails Highway (also known as Route 66) in the Mojave Desert.  The bridges are found at various locations along an approximate 111-mile segment of the roadway, between Barstow to the west and the Mountain Springs Road/I-40 entrance to the east. The following bridge numbers are included in the project: 54C0119; 54C0120; 54C0121; 54C0122; 54C0123; 54C0145; 54C0146; 54C0147; 54C0148; 54C0149; 54C0138; 54C0139; 54C0140; 54C0141; 54C0142; 54C0156; 54C0232; 54C0233; 54C0235; 54C0238; 54C0253; 54C0255; 54C0256; 54C0257; 54C0258; 54C0274; 54C0278; 54C0283; 54C0334; 54C0341; 54C0342.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete