USA logoAn Official Website of the United States Government

You are here

Mid-Barataria Sediment Diversion

Project Information
Sector: Water Resources
Project Category: 
FAST-41 Covered Projects
Project Status: 
In Progress
Total Estimated Project Cost: 
$1,400,000,000
Description: 

On June 22, 2016, CPRA submitted a joint permit application which included a brief project description:

"The Mid-Barataria Sediment Diversion is a large scale, complex civil works and ecosystem restoration project. When operated, up to 75,000 cubic feet per second (cfs) of sediment laden water would be diverted from the Mississippi River to the mid-Barataria Basin to reconnect and re-establish the natural or deltaic sediment deposition process between the Mississippi River and the Barataria Basin to deliver sediment, freshwater, and nutrients to reduce land loss and sustain wetlands."

The proposed MBSD project has the potential for significant impacts and requires an Environmental Impact Statement (EIS) under the National Envrionmental Policy Act (NEPA) to inform a permit decision relative to the lead federal agency under Section 404 of the Clean Water Act (Section 404) and Section 10 of the Rivers and Harbors Act (Section 10), and permissions under Section 14 of the Rivers and Harbors Act (Section 408) The USACE-MVN Regulatory permit processing number is MVN-2012-2806-E00.

 

Permitting Timeline

Action Agency Target Completion Status
Section 408 Permit
Milestones:
Initial application received
Complete 01/13/2017
Completed application received
Planned
Target: 12/19/2019
Issuance of decision for permit/approval
Planned
Target: 10/31/2022
Notice to proceed
Review Terminated with no decision
Optional Milestones:
District ATR Completed
Planned
Target: 07/30/2021
US Army Corps of Engineers - Civil Works 10/31/2022 In Progress
Environmental Impact Statement (EIS)
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS)
Complete 10/04/2013
Scoping
Complete 09/05/2017
Target: 09/30/2017
Official Notice of Availability of a Draft EIS published in the Federal Register
Planned
Target: 04/30/2020
Official Notice of Availability of a Final EIS published in the Federal Register
Planned
Target: 04/30/2021
Official Notice of Availability of a Supplemental Draft EIS published in the Federal Register
Official Notice of Availability of a Supplemental Final EIS published in the Federal Register
Issuance of Record of Decision or combined Final EIS / Record of Decision
Planned
Target: 06/30/2022
Issuance of an Amended Record of Decision
Planned
Target: 08/31/2022
Optional Milestones:
Decision to Prepare an EIS
Complete 08/28/2013
Updated Notice of Intent (NOI)
Complete 04/27/2017
Target: 04/30/2017
EIS Schedule/Kickoff Meeting
Complete 04/04/2017
Target: 04/30/2017
US Army Corps of Engineers - Regulatory 08/31/2022 In Progress
Clean Water Act Section 404 Permit
Milestones:
Pre-Construction Notification (PCN) / Form ENG 4345 / Joint Application Form Received
Complete 07/24/2013
Pre-Construction Notification (PCN) / Application Deemed Complete
Complete 06/22/2016
Publication of Public Notice
Final Verification / Permit Decision Rendered
Planned
Target: 10/31/2022
Optional Milestones:
Receipt of a Modified Joint Permit Application
Complete 06/22/2016
US Army Corps of Engineers - Regulatory 10/31/2022 In Progress
Section 10 Permit
Milestones:
Pre-Construction Notification (PCN) / Form ENG 4345 / Joint Application Form Received
Complete 07/24/2013
Pre-Construction Notification (PCN) / Application Deemed Complete
Complete 06/22/2016
Publication of Public Notice
Final Verification / Permit Decision Rendered
In Progress
Target: 10/31/2022
Optional Milestones:
Receipt of a Modified Joint Permit Application
Complete 06/22/2016
US Army Corps of Engineers - Regulatory 10/31/2022 In Progress
Endangered Species Act Consultation - FWS
Milestones:
Date of Request for formal consultation received
Planned
Target: 05/31/2020
Consultation Initiation Date
Planned
Target: 07/31/2020
Final Biological Opinion Issued
Planned
Target: 12/31/2021
Optional Milestones:
Ongoing Informal Consultation
Planned
Target: 05/31/2018
Fish and Wildlife Service (Cooperating under FAST-41), (Cooperating under NEPA) 12/31/2021 Planned
Fish and Wildlife Coordination Act Review
Milestones:
Initiation of coordination
Planned
Target: 04/30/2017
Completed application received
Final FWCA Report
Planned
Target: 04/30/2021
Notice to proceed
Review Terminated with no decision
Optional Milestones:
Coordination Ends
Planned
Target: 04/30/2022
Fish and Wildlife Service (Cooperating under FAST-41), (Cooperating under NEPA) 12/31/2021 Planned
Endangered Species Act Consultation - NOAA-NMFS
Milestones:
Date of Request for formal consultation received
Planned
Consultation Initiation Date
Planned
Final Biological Opinion Issued
Planned
Optional Milestones:
Additional Information Requested
Planned
National Oceanic and Atmospheric Administration (Cooperating under FAST-41), (Cooperating under NEPA) Planned
Consultation to Protect Essential Fish Habitat
Milestones:
Initial application received
Planned
Completed application received
Planned
Issuance of decision for permit/approval
Planned
Notice to proceed
Planned
Review Terminated with no decision
N/A
National Oceanic and Atmospheric Administration (Cooperating under FAST-41), (Cooperating under NEPA) Planned
Marine Mammal Protection Act Incidental Take Authorization
Milestones:
Initial application received
Planned
Completed application received
Planned
Issuance of decision for permit/approval
Planned
Notice to proceed
N/A
Review Terminated with no decision
N/A
Optional Milestones:
Publish Proposed Rule and 60 day public comment period
Planned
Publish Final Rule
Planned
National Oceanic and Atmospheric Administration (Cooperating under FAST-41), (Cooperating under NEPA) Planned
Section 106 Review
Milestones:
Initial application received
Planned
Completed application received
Issuance of decision for permit/approval
Planned
Notice to proceed
Review Terminated with no decision
Louisiana (Cooperating under FAST-41), (Cooperating under NEPA) Planned
National Environmental Policy Act (NEPA) Compliance
Milestones:
Initial application received
Complete
Completed application received
Issuance of decision for permit/approval
Complete 11/22/2016
Notice to proceed
Review Terminated with no decision
Natural Resources Conservation Service (Cooperating under FAST-41) Complete
National Environmental Policy Act (NEPA) Compliance
Milestones:
Initial application received
Planned
Completed application received
Issuance of decision for permit/approval
Planned
Notice to proceed
Review Terminated with no decision
Louisiana (Cooperating under FAST-41), (Cooperating under NEPA) Planned
National Environmental Policy Act (NEPA) Compliance
Milestones:
Initial application received
Planned
Completed application received
Issuance of decision for permit/approval.
Planned
Notice to proceed
Review Terminated with no decision
Louisiana (Cooperating under FAST-41), (Cooperating under NEPA) Planned
National Environmental Policy Act (NEPA) Compliance
Milestones:
Initial application received
Planned
Completed application received
Issuance of decision for permit/approval
Planned
Notice to proceed
Review Terminated with no decision
Louisiana (Cooperating under FAST-41) Planned
National Environmental Policy Act (NEPA) Compliance
Milestones:
Initial application received
Complete 06/22/2016
Completed application received
Issuance of decision for permit/approval
Planned
Notice to proceed
Review Terminated with no decision
Louisiana (Cooperating under FAST-41) Planned
Submit Feedback >