Long Bridge Project (DC to VA)

PROJECT WEBSITE: Long Bridge Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/30/2020

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The Federal Railroad Administration (FRA) is preparing an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act (NEPA) for the Long Bridge Project jointly with the District Department of Transportation (DDOT). The Long Bridge Project consists of potential improvements to the Long Bridge and related railroad infrastructure located between Rosslyn (RO) Interlocking in Arlington, VA to L'Enfant (LE) Interlocking near L'Enfant Plaza SW in the District.

The existing two-track Long Bridge is owned and operated by CSX Transportation (CSXT), a Class I freight railroad, which also operates the Long Bridge Corridor. In addition to CSXT freight, the bridge is also currently utilized by Amtrak and VRE.

The purpose of the Proposed Action is to provide additional long-term railroad capacity and to improve the reliability of railroad service through the Long Bridge corridor. Currently, there is insufficient capacity, resiliency, and redundancy to accommodate the projected demand in future railroad services. The Proposed Action is needed to address these issues and to ensure the Long Bridge corridor continues to serve as a critical link connecting the local, regional, and national transportation network.

______

Although not part of the Proposed Action’s Purpose and Need, the Project will explore the potential opportunity to accommodate connections that follow the trajectory of the Long Bridge Corridor to the pedestrian and bicycle network. The feasibility of this opportunity will be assessed as the Project progresses, and will consider whether a path can be designed to be consistent with railroad operator plans and pursuant to railroad safety practices. Future efforts to accommodate connections to the pedestrian and bicycle network may be advanced as part of the Project, or as part of a separate project(s) sponsored by independent entities.


In addition, pertinent information can be found at the project's FRA webpage, https://railroads.dot.gov/long-bridge-project/long-bridge-project

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete