Liberty Development and Production Plan

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE
SUBJECT TO CHANGE
7 OUT OF 9
ENVIRONMENTAL REVIEW
AND PERMITTING PROCESSES COMPLETED
SECTOR
Conventional Energy Production
CATEGORY
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior
Description: 

Hilcorp proposes to develop the Liberty Prospect in Foggy Island Bay, Beaufort Sea, Alaska by constructing an artificial drilling and production gravel island, approximately 6 miles offshore. The proposed Liberty Development described in the Development and Production Plan includes five stages: construction of the island; development of a new gravel mine; construction of a pipeline; construction of associated ice roads; and drilling and hydrocarbon production.

The island will have drilling and production processing facilities, with a single phase oil pipeline transmitting the produced sales-quality oil to shore. The island will include 16 well slots: 5-8 producers, 4-6 injectors, 2 disposal wells. Hilcorp estimates that peak production will be approximately 60,000 - 70,000 barrels per day. Estimated first production may occur in 2020-2021. The project life is estimated to be 15-20 years, with a total recovery estimate of about 167 million barrels.

Associated Permitting:

Environmental Protection Agency - NPDES Permit: Completed 10/26/2018, available here: https://www.epa.gov/npdes-permits/npdes-permit-hilcorp-alaska-liberty-drilling-and-production-island

Bureau of Safety and Environmental Enforcement - Platform Approval Program and Platform Verification Program: Tentative Decision, October 2019

Bureau of Safety and Environmental Enforcement - Application for Permit to Drill: Tentative Decision, March 2020

Bureau of Safety and Environmental Enforcement - Production Safety Systems Permitting: Tentative Decision, October 2019

Bureau of Safety and Environmental Enforcement - Oil Spill Response Plan: Tentative Decision, June 2020

Note: The project timeline represents the cooperating agencies' estimates at when agency actions could occur depending on the project proponent's future submissions. 

    Permitting Timetable

    The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

    • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.

    To view Timetable chart, please turn device sideways (landscape)

    Overall Project Timetable
    STATUS
    Schedule
    Extension
    Ahead of Schedule
    Paused

    *Planned dates are not represented in the timetable above.

    Action Information

    For additional information, please select an Action from the Permitting Timetable above.

    Action:
    Responsible Agency:
    Bureau:
    Action Status:
    SHPO:
    Action Identifier:
    Action Outcome:
    Milestone
    Original Target Date
    Current Target Date
    Milestone Complete