Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Falls International Airport Phase III/IV Runway Reconstruction and Land Acquisition Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/24/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Other Agencies with Actions or Authorizations:

Department of Transportation

Department of Transportation

Description:

The last major reconstruction project over the full length of the runway was more than 30 years ago. The EA will study alternatives to complete the runway reconstruction including maintaining airport operations during construction through use of a temporary runway on the taxiway.  The various project elements anticipated as part of the proposed action include: 
1. Reconstruction of Runway 13/31 and Taxiway Alpha
2. Clearing of the approach surfaces to Runway 13/31
3. Use of Taxiway Alpha as temporary Runway 14/32 
4. Temporary closure of Runway 4/22
5. Relocation of the Upper Air Inflation Building (balloon launch facility) – one alternative to accomplish this includes acquisition of over three acres of land. 
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete