Official US Government Icon

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

Secure Site Icon

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Downtown Los Angeles Streetcar

PROJECT WEBSITE: Downtown Los Angeles Streetcar

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/10/2019

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Project is a 3.8-mile modern fixed-rail streetcar with 23 stations running through downtown Los Angeles primarily on Hill and Broadway Avenues, and 7th and 11th Streets.  Traction power substations, a maintenance and storage facility, right-of-way and rail cars will be acquired for the Project.

The Project will begin at Hill and 1st Streets, run east along 1st Street, south along Broadway, west along 11th Street, north along Figueroa Street, east along 7th Street, and north along Hill Street, back to its beginning at 1st Street. The Potential inclusion of a Grand Avenue Extension as a design option would also provide a two-way alignment spur west along 1st Street, beginning at Hill Street, and continuing south along Grand Avenue to a stop north of 2nd Street.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete