Derry, Londonderry, Exit 4A, I-93 (State Number 13065)

PROJECT WEBSITE: I93 EXIT 4A PROJECT Derry & Londonderry, New Hampshire

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

4 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The Towns of Derry and Londonderry (the Towns) and the New Hampshire Department of Transportation (NHDOT), in cooperation with the Federal Highway Administration (FHWA), are advancing an updated environmental study for the I-93 Exit 4A Project (Project). The Project consists of a new diamond interchange on I-93 in the Town of Londonderry, approximately one mile north of Exit 4. The new diamond interchange would provide access to the east side of I-93. A 1-mile connector roadway would be built on new alignment from the interchange to Folsom Road, near the intersection of North High Street and Madden Road, in the Town of Derry. Folsom Road, and subsequently Tsienneto Road, would be upgraded, and the intersections would be improved. In total, the Proposed Project corridor from I-93 to the intersection of Tsienneto Road and NH Route 102/Chester Road would be 3.2 miles. The purpose of the Project is to reduce congestion and improve safety along NH 102, from I-93 easterly through downtown Derry and to promote economic vitality in the Derry/Londonderry area.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete