Dallas to Houston High Speed Rail

PROJECT WEBSITE: Dallas to Houston High-Speed Rail – Passenger Service from Houston to Dallas

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/31/2020

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The Dallas to Houston High Speed Rail Project would provide high speed rail service between Dallas, TX and Houston, TX utilizing the N-700I Tokaido Shinkansen system from Japan.  Three stations are proposed as part of the project: one terminal station in Dallas, one intermediate Brazos Valley Station in Grimes County, and one terminal station in Houston.

Current FRA regulations do not address equipment requirements for train speeds above 150 miles per hour (mph). Therefore, before the project can operate in the United States FRA may issue a Rule of Particular Applicability (regulations that apply to a specific railroad or a specific type of operation), a series of waivers or take another action to ensure the Project is operated safely. This regulatory action(s) constitutes a major federal action and triggers the environmental review under NEPA.

Currently, this project is 100% privately funded.


In addition, pertinent information can be found at the project's FRA webpage, https://railroads.dot.gov/dallas-houston-high-speed-rail/dallas-houston-high-speed-rail-passenger-service-houston-dallas

 

FRA released the Final EIS on May 29, 2020:  https://railroads.dot.gov/elibrary/dallas-houston-high-speed-rail-project-list-repositories-within-project-area

 

Following a minimum 30-day waiting period announced in the Federal Register on May 29, 2020, during at which time agencies and the public may review the Final EIS, FRA anticipates preparing a Record of Decision, documenting FRA’s decision, the alternatives considered in the EIS, the environmentally preferable alternative, and summarizing the required mitigation measures.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete