Dallas Central Business District Second Light Rail Alignment (D2)

PROJECT WEBSITE: Dallas Central Business District (CBD) Second Light Rail Alignment Project Webs…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/01/2020

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Downtown Dallas Transit Project is studying the options for a second Dallas Area Rapid Transit (DART) light rail alignment through downtown. A Draft EIS was circulated in March 2010. The proposed D2 Project consists of approximately 2.4 miles light rail alignment with up to five new light rail stations in the Central Business District of Dallas. A Locally Preferred Alternative and design options are being studied. The D2 Project will increase system capacity, provide operational flexibility, and serve new markets.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete