Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Coos Bay, Oregon Section 408/204(f) Channel Modification

PROJECT WEBSITE: Coos Bay Proposed Channel Modification

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Ports and Waterways icon

SECTOR
Ports and Waterways

CATEGORY
Major Infrastructure Projects

Department of the Army icon

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Civil Works

Other Agencies with Actions or Authorizations:

Department of Commerce icon

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army icon

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior icon

Department of the Interior, Fish and Wildlife Service

Description:

The Oregon International Port of Coos Bay (OIPCB) proposes to widen and deepen the Coos Bay Federal Navigation Project from the ocean to river mile (RM) 8.2 to improve navigation efficiency, reduce shipping transportation costs, and facilitate the shipping industry’s transition to larger, more efficient vessels.  The OIPCB is using an authority provided by the U.S. Congress under Section 204 of the Water Resources Development Act of 1986, as amended.

The Port is coordinating with the U.S. Army Corps of Engineers (USACE), Portland District on the design and engineering of the proposed alteration and long-term maintenance of the channel.  The OIPCB is evaluating channel modifications and maintenance dredging of the channel and inlet; possible modifications to the jetties would also be evaluated.  This is a single-purpose study for deep draft navigation.  Physical construction cannot commence until the 33 USC 408 permission and Section 404 (CWA) permit are received from the Corps of Engineers.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete