Chokecherry/Sierra Madre Wind, Phase II

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
PAUSED
ESTIMATED COMPLETION DATE
SUBJECT TO CHANGE
0 OUT OF 3
ENVIRONMENTAL REVIEW
AND PERMITTING PROCESSES COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior
Description: 

The Chokecherry and Sierra Madre (CCSM) Wind Energy Project was proposed by the Power Company of Wyoming (PCW) in 2008. The project consists of two wind development areas, Chokecherry and Sierra Madre. The two wind development areas, comprise a 219,707-acre conceptual area of development of mixed public and private land located about 10 miles south of Rawlins, Wyoming. The CCSM Environmental Impact Statement (EIS) Record of Decision (ROD) was completed and signed on October 9, 2012.  The CCSM project was analyzed under a programmatic Environmental Impact Statement and the Record of Decision was signed by the Secretary of the Interior on October 9, 2012. In the ROD, BLM determined that over 200,000 acres within the CCSM Project Area are suitable for wind energy development subject to the requirements described under the Selected Alternative in the ROD. Phase II of the project includes construction of turbines in the second wind development area.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.

To view Timetable chart, please turn device sideways (landscape)

Overall Project Timetable
STATUS
Schedule
Extension
Ahead of Schedule
Paused

Action Information

For additional information, please select an Action from the Permitting Timetable above.

Action:
Responsible Agency:
Bureau:
Action Status:
SHPO:
Action Identifier:
Action Outcome:
Milestone
Original Target Date
Current Target Date
Milestone Complete