Chincoteague Recreational Beach Road and Parking Relocation
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/08/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The Environmental Assessment for the Recreational Beach Relocation Project at Chincoteague National Wildlife Refuge analyzes the proposed action for the site design of the facilities needed to support the relocation of the recreational beach, as described in the August 2015 Final Comprehensive Conservation Plan and Environmental Impact Statement and approved by the Record of Decision signed on November 6, 2015. The proposed action would configure the parking areas, roads, and related facilities needed to access and support the use of the new recreational beach. Included in the proposed action is the: construction of a new two-lane access road and roundabout intersection; improvement of the entrance fee booth area; new parking areas and paths to access the new recreational beach; vault toilets, rinse-off showers, foul weather shelters, changing room cabanas and other facilities needed to provide a safe and appropriate beach recreation experience; a new multi-use trail; replacement of the water control structures on C- and D-dikes; relocation of the NPS staff offices and educational programs currently residing at Toms Cove Visitor Center; and, a new parking area at the South Pony Corral.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|