Buffalo Bayou and Tributaries, Texas Resiliency Study

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources icon

SECTOR
Water Resources

CATEGORY
Major Infrastructure Projects

Department of the Army icon

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Civil Works

Description:

USACE, in partnership with the Harris County Flood Control District (HCFCD), as the non-Federal sponsor, is undertaking the study to evaluate the feasibility of reducing flood risks on Buffalo Bayou upstream and downstream of Addicks and Barker Reservoirs.   The Buffalo Bayou and Tributaries, Texas Project (Project) was authorized by Congress in the 1930s for the purpose of providing flood control for the city and port of Houston, Texas. In the 1940s, Addicks and Barker Dams were constructed and a portion of Buffalo Bayou was straightened as part of the completed Project. Since the 1940s, a number of physical improvements and operational changes to the Project have been implemented. However, the watershed continues to experience major flood events, with the most recent and most significant occurring during Hurricane Harvey in 2017. These recent flood events, coupled with projected increases in precipitation patterns and the potential for flooding events in the future, warrant investigation into whether the Project should be modified to address existing and future flooding concerns.

 

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete