USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Bay State Wind Project

PERMITTING DASHBOARD PROJECT POSTING DATE: MARCH 07, 2018

PROJECT WEBSITE: Bay State Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Cancelled

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

The Starboard Wind Project will be developed by Bay State Wind LLC, a wholly owned subsidiary of Ørsted. The area to be developed is within the Outer Continental Shelf covered by the Bureau of Ocean Energy Management (BOEM) Renewable Lease No. OCS-A 0500 (Lease Area). The Lease Area is located approximately 14 miles (mi, 22.5 kilometers [km]) south of Martha’s Vineyard, Massachusetts. The Starboard Wind Project represents an update to the Bay State Wind COP, which was submitted in 2019.

The Starboard Wind Project has withdrawn from the FAST-41 Dashboard but continues to engage with BOEM through the permitting process.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete