Alkali Creek Reservoir Project

PROJECT WEBSITE: Alkali Creek Reservoir Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/30/2020

4 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources icon

SECTOR
Water Resources

CATEGORY
Major Infrastructure Projects

Department of the Interior icon

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

The State of Wyoming Water Development Commission (WWDC) proposes to construct a 294-acre reservoir on Alkali Creek and ancillary facilities across public and private land near Hyattville, Wyoming. The reservoir would impound approximately 7,994 acre-feet of water under normal conditions, and 9,872 acre-feet when under flood conditions. The reservoir would provide late-season irrigation water for portions of the Nowood River Watershed. The irrigation pool would be available either directly or through exchange for irrigation water.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete