ACEforward

Project Information
Sector: Surface Transportation
Project Category: 
DOT Projects
Project Status: 
Cancelled
Description: 

The FRA published in the Federal Register (83 FR 61709-10) on November 30, 2018, a notice to advise the public that FRA is rescinding the Notice of Intent (NOI) for the ACEforward Program.  The project sponsor has determined that the original scope for the ACEforward Environmental Impact Statement (EIS) is no longer consistent with regional planning efforts for improved rail service throughout the corridor.

The San Joaquin Regional Rail Commission (SJRRC) is launching an effort to improve and expand the existing Altamont Corridor Express (ACE) rail service between Stockton and San Jose, California, as well as extension of the rail service to Modesto and Merced, California. The ACEforward program will strive to reduce travel time by at least 10 percent, and increase reliability of the existing ACE rail service. In the near term, ACEforward aims to increase existing service from 4 daily round trips to a proposed 6 daily round trips, extend to Modesto in Stanislaus County, implement safety and grade crossings improvements, and add track in key locations. ACEforward is also planning longer-term improvements to increase service to at least 10 daily round trips, provide weekend service, and extend to Merced. As of  June 6, 2013, project leadership and funding for the Altamont Corridor has been transferred from the California High-Speed Rail Authority to the San Joaquin Regional Rail Commission.

In addition, pertinent information about the project can be found at the project's FRA webpage: https://www.fra.dot.gov/Page/P0663

Permitting Timeline

Environmental Impact Statement (EIS)
Federal Railroad Administration
Cancelled
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) 
Complete 09/18/2013
Scoping 
Complete 10/17/2013
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review
Current Target Date: 01/31/2019
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review 
Current Target Date: 09/30/2019
Issuance of Record of Decision or combined Final EIS / Record of Decision 
Current Target Date: 11/29/2019
Section 106 Review
Federal Railroad Administration
Cancelled
Milestones:
Consultation initiated with SHPO/THPO
Complete 09/18/2013
Section 106 consultation concluded
Current Target Date: 11/29/2019