Westside Purple Line Extension Phase II

PROJECT WEBSITE: Westside Purple Line

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/01/2017

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Purple Line Extension Transit Project is a critically important rail project that will provide a high-capacity, high-speed, dependable alternative for commuters to travel between downtown Los Angeles and Westwood in just 25 minutes. The extension will be built in three sections and will continue from the current station at Wilshire/Western, extending westward for about nine miles along Wilshire Bl. The extension will include seven new stations at Wilshire/La Brea, Wilshire/Fairfax, Wilshire/La Cienega, Wilshire/Rodeo, Century City/Constellation, Westwood/UCLA, and Westwood/VA Hospital.This new Metro Rail extension will offer an alternative transportation option to congested roadways, provide significant environmental benefits and spur economic development throughout the county. Through improved connectivity, riders will be better able to use the entire Metro Rail system, municipal bus lines and other regional transportation services.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete