Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Stibnite Gold Project

PROJECT WEBSITE: https://www.fs.usda.gov/project/?project=50516

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Other icon

SECTOR
Other

CATEGORY
Other Projects

Department of Agriculture icon

LEAD AGENCY
Department of Agriculture, US Forest Service

Other Agencies with Actions or Authorizations:

Advisory Council on Historic Preservation icon

Advisory Council on Historic Preservation

Department of the Army icon

Department of the Army

Department of the Interior icon

Department of the Interior, Fish and Wildlife Service

Description:

The Stibnite Gold Project (SGP) consists of a mine site and processing facilities, associated access roads, and off-site facilities located in Valley County, in central Idaho. The mine site is located in the East Fork South Fork Salmon River (EFSFSR) drainage basin. The SGP area is a complex blend of both remote wilderness lands with high recreational values and potential wilderness characteristics, and areas impacted by historical gold, silver, antimony, and tungsten mining, processing, and resulting legacy contamination. The potentially affected area encompasses approximately 3,500 acres.

Midas Gold’s plan of operations to conduct mining operations that produce gold and silver oré, and antimony concentrates, includes open pits, ore transportation equipment, ore processing facilities, development rock storage facilities, a tailing storage facility, a water treatment facility, road construction, electrical transmission lines, and various other facilities needed to support mining activities.

The plan of operations incorporates closure and reclamation activities, and mitigation that may avoid, minimize, or compensate for adverse environmental effects caused by the SGP, and also incorporates actions that mitigate legacy contamination at locations within the mine site. Under the plan of operations, construction, operation, closure and reclamation phases of the SGP would take place over a period of approximately 20 years, not including the period of time required for long-term monitoring and maintenance. Environmental monitoring and maintenance would continue for as long as needed to demonstrate that the site has been fully reclaimed.

This is a hardrock mine and legacy clean up project that incorporates development and production of a listed critical mineral (antimony), gold and supporting infrastructure.

The purpose and objectives for the Project for Midas Gold are to:

• Economically develop and operate a modern mining operation at the Stibnite site;

• Fund the reclamation and restoration aspects of the Project;

• Obtain financial return and benefits from its property rights and investment; and

• Supply extracted minerals for various uses, including antimony which is a designated critical mineral and essential to support renewable energy generation and manufacturing processes.

This would be accomplished while providing broader environmental restoration and socioeconomic benefits at the site and for the surrounding area.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete