State Route 37 Sears Point to Mare Island Improvement Project
PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-4/d4-projects/d4-37-corridor-proje…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/14/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans)—in cooperation with the Metropolitan Transportation Commission (MTC) and the north bay partner agencies of Sonoma County Transportation Authority (SCTA), Solano Transportation Authority (STA), and Napa Valley Transportation Authority (NVTA)—is proposing improvements to the portion of State Route (SR) 37 that is one lane in each direction. Caltrans is the lead agency under CEQA and NEPA.
The section of SR 37 proposed for widening is a two-lane conventional highway between SR 121 and the Mare Island Interchange (approximately 9 miles). East of the Mare Island, Interchange SR 37 is a four-lane freeway facility between Interstate 80 (I-80) and Mare Island (approximately 4.5 miles). West of SR 121, it is a four-lane conventional highway between SR 121 and United States Highway 101 (U.S. 101) (approximately 7.3 miles). The highway allows local road and driveway access from adjoining properties, has acceleration and deceleration lanes at some local intersections, and has an existing median barrier along most of the route. Bridge crossings are at Sonoma and Tolay creeks.
The project is within or adjoins the counties of Sonoma, Solano, and Napa and would add a high-occupancy vehicle (HOV) lane(s) from just west of SR 121 to the Mare Island (Walnut Avenue) Overcrossing, within the portion of SR 37 that is currently served by only one lane in each direction. Four alternatives are being considered. Each of the four Build Alternatives would reconfigure the existing SR 37 highway lanes from west of the SR 121 intersection to the Walnut Avenue Overcrossing at Mare Island. Each alternative would involve widening the existing bridge over Tolay Creek.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|