The project sponsor filed an application for an original license on January 23, 2025. The application and other supporting documents can be found by searching under docket number P-15094 in the Commission's eLibrary system.
On September 28, 2026, Commission staff issued an Environmental Assessment discussing proposed and recommended environmental measures for the proposed project.
There is no active litigation on the Commission's licensing proceeding.
Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available.
- On September 25, 2025, the Commission issued a notice establishing a deadline for filing scoping comments.
- On January 14, 2026, the Commission issued a notice establishing a deadline for filing comments, recommendations, terms and conditions, and prescriptions.
- On September 28, 2026, the Commission issued a notice with information on submitting comments on the Environmental Assessment.
- On February 6, 2025, the Commission issued a Notice of Application Tendered for Filing with the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule.
- On March 27, 2025, the Commission issued a Notice of Revised Procedural Schedule.
- On July 3, 2025, the Commission issued a Notice of Application Accepted for Filing and Soliciting Motions to Intervene and Protests.
- On September 25, 2025, the Commission issued a Notice Soliciting Scoping Comments and Procedural Schedule.
- On January 14, 2026, the Commission issued a Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions; Intent to Prepare an Environmental Assessment; and Anticipated Schedule.
- On January 28, 2026, the Commission issued a Notice of Schedule for the Final License Order.
- On September 28, 2026, Commission staff issued an Environmental Assessment.