MVP Southgate CP19-14
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/18/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
Other Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Other Agencies with Actions or Authorizations:
Federal Energy Regulatory Commission, Office of Energy Projects
Department of the Interior, Fish and Wildlife Service
Description:
On June 18, 2020, the Commission issued a certificate order in Docket No. CP19-14-000 authorizing the project sponsor to construct and operate the MVP Southgate Project, including approximately 75 miles of natural gas pipeline and associated aboveground facilities in Pittsylvania County, Virginia, and Rockingham and Alamance Counties, North Carolina. On February 3, 2025, the project sponsor filed an application in Docket No. CP25-60-000 requesting to amend the certificate for the MVP Southgate Project issued by the Commission in Docket No. CP19-14-000. Among other changes, the project sponsor proposed to reduce the length of the pipeline route from 75 miles to 31.3 miles. On December 18, 2025, the Commission issued an order amending the certificate.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|