Official US Government Icon

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

Secure Site Icon

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Minneapolis-St. Paul to Milwaukee High-Speed Rail Corridor

PROJECT WEBSITE: Minneapolis/St. Paul - Milwaukee High-Speed Rail: Tier 1 Environmental Impact S…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Cancelled icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The Federal Railroad Administration (FRA) published in the Federal Register on November 30, 2018, a notice to advise the public that FRA is rescinding the Notice of Intent (NOI) for the Minneapolis/St. Paul - Milwaukee High-Speed Rail Corridor. The project sponsor and FRA have agreed to rescind the NOI; however, the associated alternatives analysis and service development plan may be used for further environmental reviews where necessary.

FRA has approved the release of the Final Alternatives Selection Report by the Minnesota Department of Transportation (MnDOT), which describes the methodology and analysis that was conducted to identify "reasonable and feasible passenger rail alternative(s)." The report identifies one route (Route 1, the existing Amtrak route from Milwaukee-Watertown-Portage-Tomah-La Crosse-Winona-Hastings-St. Paul-Minneapolis) as the most reasonable and feasible passenger rail alternative. The route provides an opportunity to incrementally use a reduction in travel time and increase train frequency by phasing the build-out of the route, according to the report. This phased approach recognizes the constraints associated with funding requirements for major infrastructure improvements and is consistent with the Minnesota Statewide Rail PlanExternal Link.

The FRA in cooperation with MnDOT is in the process of preparing a Tier 1 Service Level Environmental Impact Statement for improved passenger rail service from the Twin Cities to Milwaukee and the Notice of Intent to initiate the environmental study was published in 2013.

The environmental impact statement (EIS) of the Twin Cities to Milwaukee High-Speed Rail Corridor to Chicago will analyze improvements required for the implementation of regional intercity passenger rail service in the Minneapolis-St. Paul to Milwaukee corridor. The proposed improvements will help complete the Midwest Regional Rail InitiativeExternal Link (MWRRI) vision for developing an improved and expanded passenger rail system in the Midwest. The proposed service will eventually link to the existing Amtrak Hiawatha serviceExternal Link between Milwaukee and Chicago. This study will be a major step in advancing passenger rail service in this highly populated corridor and extending service from Chicago to the Twin Cities.

The Tier 1 EIS document will evaluate one or more service scenarios of the reasonable and feasible passenger rail alternative and a no build alternative. The evaluation will be based on:

  • Conceptual Engineering
  • Track Concepts
  • Capital Cost Estimate
  • Station Location Analysis
  • Environmental Analysis
  • Ridership
  • Operating Costs
  • Assessment of Benefits

Next steps

Upon the conclusion of the Tier 1 study a detailed environmental analysis of the corridor and individual projects along the corridor will be identified to be studied in Tier 2 (Preliminary Engineering - PE phase) study.


In addition, pertinent information can be found at the project's FRA webpage, https://railroads.dot.gov/environment/current-environmental-reviews/minneapolisst-paul-milwaukee-high-speed-rail-tier-1

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete