Lynnwood Link Extension (Light Rail Transit)
PROJECT WEBSITE: Lynnwood Link Extension
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/10/2015
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Transit Administration
Other Agencies with Actions or Authorizations:

Washington
Description:
The Central Puget Sound Regional Transit Authority (Sound Transit) is proposing to extend its light rail system from Northgate Station in Seattle, WA, north to Lynnwood Transit Center in Lynnwood. The 8.5-mile-long alignment would combine at-grade and elevated guideway primarily within the Interstate 5 right-of-way, with three stations between the termini. This is the primary route serving a large and growing commuter market between Snohomish and King counties, and is part of the state's major north-south freeway. It is one of the most densely developing areas in the Pacific Northwest; roadways in the corridor experience high levels of congestion, degrading mobility, and reliability.
*This project was identified Regionally or Nationally Significant in the original Permitting Dashboard
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|