Kake to Petersburg Transmission Project

PROJECT WEBSITE: http://www.seapahydro.org/Kake-Petersburg-Intertie.php#div1

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/30/2016

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission icon

SECTOR
Electricity Transmission

CATEGORY
FAST-41 Covered Projects

Department of Agriculture icon

LEAD AGENCY
Department of Agriculture, US Forest Service

Description:

69kV/138kV  would connect this isolated electric system to the interconnected electric systems of
Petersburg, Wrangell and Ketchikan. Petersburg, Wrangell, and Ketchikan are currently interconnected to and obtain most of their power supplies from the Tyee Lake and Swan Lake hydroelectric projects owned by the Southeast Alaska Power Agency (SEAPA) (formerly the Four Dam Pool Power Agency).
The Kake-Petersburg Intertie would be used to transmit surplus hydroelectric power from SEAPA to the electric system in Kake, thereby offsetting the existing diesel generation while lowering and stabilizing the cost of electricity in Kake.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete