USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Muncy Creek Mineral Exploration Project

PROJECT WEBSITE: https://www.fs.usda.gov/r04/humboldt-toiyabe/projects/62350

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/09/2026

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, US Forest Service

Description:

The Muncy Creek Exploration Plan of Operations was proposed by Falcon Copper as a part of their Schell Creek exploration project.  The Muncy Creek Plan proposes mineral exploration for copper, zinc, molybdenum, and silver in the Ely Ranger District of the Humboldt-Toiyabe National Forest in White Pine County Nevada.  Exploration activities are proposed to occur in phases and include up to 15 drill pads constructed, exploration drilling, 2.3 miles of road construction, and road maintenance. Phase I includes the construction of six drill sites with nine additional drill sites proposed over additional phases. 

This project is posted in the interest of transparency and response to Executive Order 14241.

  

 

 

 
 
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete