USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Grassy Mountain Mine Project

PROJECT WEBSITE: Grassy Mountain Mine Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/01/2026

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View Postings by Agencies

Description:

The project sponsor proposes to construct, operate, reclaim, and close an underground mining and precious metal milling operation known as the Grassy Mountain Mine Project.

The project would consist of a mine and process plant area and a project access area. Access to the mine would be along an existing road, though road improvements would need to be made to accommodate large mining vehicles. The project sponsor proposes to mine approximately 2.07 million tons of mill grade ore and 0.27 tons of waste rock for a mine life of approximately 8 years. The project would result in approximately 487.9 acres of proposed surface disturbance on 18.9 acres of private land and 469 acres of public land.

This project is posted in the interest of transparency and response to Executive Order 14241.

 
 
 
 
 
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete