3PL Railroad Valley Exploration Project
PROJECT WEBSITE: 3PL Railroad Valley Exploration Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/05/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Transparency Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
This project is posted in the interest of transparency and response to Executive Order 14241.
The project sponsor proposes conducting mineral exploration activities on public land within a 24,427-acre Project Area. The project area contains approximately 39.2 acres of disturbance within the 24,727-acre Project Area. Surface disturbing activities would consist of utilizing the existing road network for project access, exploration drill pads, access roads, exploration wells, cellars, sumps, up to two work yards, bulk sampling, geotechnical auger holes, geological test pits and geological and geophysical mapping. In addition, minor road maintenance and repair would include snow removal and filling holes with clean, weed-free, fill material or gravel, to provide safe and durable running surfaces. The project sponsor proposes to conduct exploration well drilling and brine testing on up to five new constructed drill sites and continued studies of the three wells drilled under Notice NVN-100052.
The project is located on BLM-administered public lands.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|