Swan Lake North Pumped Storage
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016PROJECT WEBSITE: http://www.ryedevelopment.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/17/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Description:
Swan Lake North Pumped Storage (Project No. 13318) is a proposal to construct an original, closed-loop pumped storage project that would provide 393 MW of generation capacity in Oregon. The proposed project would consist of, among other facilities, an upper and lower reservoir with active storage capacities of 2,562 and 2,581 acre-feet, respectively, a high-pressure penstock, three low-pressure penstocks, a powerhouse, a substation, and a 32.8-mile-long, 230-kilovolt transmission line.
Project Application and Supporting Documents
- Swan Lake North Hydroelectric Project, Initial Statement of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029230.
- Swan Lake North Hydroelectric Project, Exhibit A of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029232.
- Swan Lake North Hydroelectric Project, Exhibit B of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029298.
- Swan Lake North Hydroelectric Project, Exhibit C of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029292.
- Swan Lake North Hydroelectric Project, Exhibit D of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029259.
- Swan Lake North Hydroelectric Project, Exhibit E of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029276.
- Swan Lake North Hydroelectric Project, Exhibit F of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029280.
- Swan Lake North Hydroelectric Project, Exhibit G of Project Application, FERC Docket No. P-13318 (filed 10/28/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14029263.
- Additional Project-related filings and issuances can be found on FERC’s eLibrary website by searching under Docket No. P-13318.
Federal Agency Actions
- Federal Energy Regulatory Commission, Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions (issued 12/20/2017). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14780889.
- Federal Energy Regulatory Commission, Draft Environmental Impact Statement (issued 08/22/2018). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=15001828.
- Federal Energy Regulatory Commission, Final Environmental Impact Statement (issued 01/25/2019). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=15147474.
- Federal Energy Regulatory Commission, Order Issuing Original License (issued 04/30/2019). Document located at: https://elibrary.ferc.gov/idmws/common/OpenNat.asp?fileID=15233738.
FERC Litigation
- None filed.
Last updated November 22, 2019
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|