USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

South Railroad Mine Project

PERMITTING DASHBOARD PROJECT POSTING DATE: NOVEMBER 05, 2025

PROJECT WEBSITE: https://orlamining.com/asset/south-carlin-complex/south-railroad-project/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/13/2026

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

Orla Mining/Gold Standard Ventures (US) is proposing to construct, operate and reclaim a new gold and silver mine from which ore would be extracted using conventional surface mining techniques and associated facilities. Ore extraction would occur in 4 open pits; 2 of which would require dewatering and result in the formation of post-mining pit lakes. The proposed mine plan boundary includes 8,548 acres, consisting of a 7,158-acre mining area and 1,390-acre access road area. Of the 8,548 acres, approximately 4,624 acres are on BLM-administered lands and 3,924 acres are on fee simple private lands. In total, 1,770 acres of surface disturbance would occur, with 839 acres of that disturbance on the private land and 931 acres on BLM-administered land. 1,267 acres of the disturbance would be temporary, and 503 acres would be permanent disturbance.  The life of the proposed action is approximately 16.5 years and includes approximately 1.5 years for construction, 10 years for operations, and 5 years for reclamation.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete